File #: 24-620    Version: 1 Name:
Type: Agenda Status: Agenda Ready
File created: 10/22/2024 In control: City Council
On agenda: 12/10/2024 Final action:
Title: Approve a multi-year contract for full-depth pavement reclamation with Asphalt Paving Systems piggy-backing off the Citrus County contract ITB 24-088 in the amount of $366,565 for Range Road. Approve additional milling and paving from Goodson Paving, Inc. piggy-backing off the Brevard County contract B-6-23-70, in the amount of $267,908 for Range Road. Approve striping with Fausnight Line and Stripe piggy-backing off the existing Seminole County contract IFB-604562-23 in the amount of $27,290. Approve BAF 25-011-PT. Authorize the City Manager to sign the related agreements and multi-year contract renewals. Authorize the City Manager to issue the purchase orders. Approve a contingency resolution authorizing the City Manager to approve and execute change orders in an amount not to exceed $50,000 for a total project cost of $711,763.
Attachments: 1. 102224 - Asphalt Paving Systems - Range Rd - FDR - $366,564.05.pdf, 2. PARTIALLY EXECUTED Piggyback Contract No. ITB 24-088 (Asphalt Paving Systems).pdf, 3. 101824 - Goodson Paving Proposal - Range Road - $267,907.60.pdf, 4. 102824 - Fausnight - Range Road Striping - $27,290.00.pdf, 5. 083123 - B-6-23-70 - Notice_of_Award (Goodson Paving).pdf, 6. 112823 - Agenda 23-714 Journal - IFB-604562-23LNF (Fausnight).pdf, 7. B-6-23-70 Asphalt - Bid_Tabulation (Goodson Paving).pdf, 8. B-6-23-70_FINAL_INC&SPECS_Asphaltic_Concrete(Goodson).pdf, 9. FULLY EXECUTED Piggyback Agreement_B-6-23-70 Asphalt(Goodson).pdf, 10. FULLY EXECUTED Piggyback Contract No. IFB-604562-23LNF(Fausnight).pdf, 11. IFB-604562-23_(Fausnight)_Executed.pdf, 12. ITB 24-088 Executed Agreement (Asphalt Paving Systems).pdf, 13. ITB-24-088 - BID TABULATION COMPLETE (Asphalt Paving Systems).pdf, 14. SIGNED Renewal Letter-(Goodson Paving).pdf, 15. Contingency Resolution for Paving.pdf, 16. BAF# 25-011-PT-Range Road Full Depth Paving (12-10-24) Agenda 24-620.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

Memo Date:                                          October 22, 2024

Agenda Date:                     December 10, 2024

Prepared By:                                          Frank Mirabito, Streets & Stormwater Manager

Through:                                          Abigail Morgan, P.E. - Public Works Director/City Engineer

Requested Action:                     

title

Approve a multi-year contract for full-depth pavement reclamation with Asphalt Paving Systems piggy-backing off the Citrus County contract ITB 24-088 in the amount of $366,565 for Range Road.  Approve additional milling and paving from Goodson Paving, Inc. piggy-backing off the Brevard County contract B-6-23-70, in the amount of $267,908 for Range Road.  Approve striping with Fausnight Line and Stripe piggy-backing off the existing Seminole County contract IFB-604562-23 in the amount of $27,290. Approve BAF 25-011-PT.  Authorize the City Manager to sign the related agreements and multi-year contract renewals.  Authorize the City Manager to issue the purchase orders.  Approve a contingency resolution authorizing the City Manager to approve and execute change orders in an amount not to exceed $50,000 for a total project cost of $711,763.

End

 

body

BACKGROUND:

 

Public Works has received several complaints about the condition of Range Road.  Consultants were tasked with assessing the condition of the Range Road pavement in May of 2024.  The report recommended full-depth reclamation for a portion of Range Road from Cocoa Bay south to the City limits, and regular milling and paving for the remaining portion from Cocoa Bay to Rice Drive.

 

During the budgeting process for Fiscal Year 2025, Range Road from the City limits on the south side to Rice Drive was identified as a candidate for full depth reclamation.  Full depth reclamation (FDR) is a pavement rehabilitation technique in which the full flexible pavement section and a predetermined portion of the underlying materials are uniformly pulverized and blended together to produce a homogeneous stabilized base course (SBC).  Approximately $135,000 will be diverted from the City’s annual street paving program to complete this work in Fiscal Year 2025.

 

Asphalt Paving Systems, Inc. has previously performed pavement projects in the City and provides FDR services. Pineda Street previously received FDR treatment.  This agenda establishes a multi-year piggyback off of the Citrus County Countywide Resurfacing and Preservation Projects ITB 24-088.

 

Goodson Paving, Inc. does not offer FDR services but does pave over the FDR surface.  The City is piggybacking off of the Brevard County Paving Contract B-8-23-09.  The City of Cocoa will retain the millings from this project.  This piggyback is for one year.

 

Fausnight Line and Stripe will be striping the completed pavement surface.  The City has an existing multi-year piggyback utilizing Seminole County Contract IFB-604562-23.  This funding was already budgeted.

 

The $50,000 for Contingency will not be included in the initial purchase order.  Each change order will be reviewed by staff before it is sent to the City Manager for approval and added to the purchase order.

 

City Staff recommends utilizing Asphalt Paving Systems, Inc. to perform FDR on Range Road and is seeking an 8% contingency in the event there are deficiencies uncovered during the construction process.  Goodson Paving will provide additional milling and paving activities.  Fausnight Line and Stripe will be striping the completed pavement surface.

 

 

STRATEGIC PLAN CONNECTION: 

 

This project identifies infrastructure needs and incorporates them based on the analysis completed.

 

 

BUDGETARY IMPACT:

 

Budgeted                                                                                                                                                   Yes

If not budgeted, is amendment/transfer attached?                     Yes

 

$550,000 (Budgeted in FY25) 001-3510-541.63-00 Project PW24RR

 

 

Amount Requested                                            ($134,473)

Account Number                                          _001-3510-541.63-00 PW08SP

Account Name                                          _Streets - Infrastructure

 

Amount Requested                                            $134,473

Account Number                                          _001-3510-541.63-00 PW24RR

Account Name                                          _Streets - Infrastructure

 

Total Budget Capital Paving $684,743, Inclusive of $50,000 Contingency

 

Striping

Amount Requested                                            $27,290

Account Number                                          _001-3510-541.46-00

Account Name                                          _Streets - Repair and Maintenance

 

BAF 25-011 Project Transfer

 

 

PREVIOUS ACTION:

 

On June 10, 2020 Council approved Full Depth Reclamation for Pineda Street.

 

RECOMMENDED MOTION:

Recommendation

Approve a multi-year contract for full-depth pavement reclamation with Asphalt Paving Systems piggy-backing off the Citrus County contract ITB 24-088 in the amount of $366,565 for Range Road.  Approve additional milling and paving from Goodson Paving, Inc. piggy-backing off the Brevard County contract B-6-23-70, in the amount of $267,908 for Range Road.  Approve striping with Fausnight Line and Stripe piggy-backing off the existing Seminole County contract IFB-604562-23 in the amount of $27,290. Approve BAF 25-011-PT.  Authorize the City Manager to sign the related agreements and multi-year contract renewals.  Authorize the City Manager to issue the purchase orders.  Approve a contingency resolution authorizing the City Manager to approve and execute change orders in an amount not to exceed $50,000 for a total project cost of $711,763.