CITY COUNCIL AGENDA ITEM
Memo Date: May 15, 2023
Agenda Date: June 6, 2023
Prepared By: Katherine D. Ennis, P.E., Deputy Utilities Director
Through: John A. Walsh, P.E., Utilities Director
Requested Action:
title
Approve a Budget Resolution, Amending the FY2023 Budget, BAF# 23-080-T in the amount of $231,146; Approve Change Order #1 for Elenis Contracting LLC/PO 80847 in the amount of $231,146; Approve Project Resolution Authorizing the City Manager to Issue Change Orders with a Total Project Contingency not to exceed $273,559 for the Dyal Ground Water Filter #3 Project (WS23DF)
End
body
BACKGROUND:
On March 14, 2023 Council approved award of the project to Elenis Contracting LLC in the amount of $424,120. Council also authorized the City Manager to Approve and Execute Change Orders in an Amount Not to Exceed $42,412 (10% of the Contract Amount).
The dual media filters at the Dyal Water Treatment Plant are used to remove suspended solids from water. The filters are cleaned periodically with water and air so that the media can be reused. With time, however, the media exhausts its removal capabilities and needs to be exchanged.
This project’s original scope was for the replacement of the media, as well as parts of the underdrain system (the IMS caps), which have become clogged with sediment and scaling in filter #3. An inspection of the filter equipment was performed by the contractor and the manufacturer of the equipment (Leopold) once the exhausted media had been removed from the filter. It was determined that there is damage to the underdrains which will require replacement. This additional scope was not known at the time of bid.
The contractor has submitted a quote for the additional scope. The cost for this additional work is $231,146 which is greater than the current available contingency amount.
Staff is requesting approval of the budget resolution, project contingency resolution, and the approval of Change Order #1 in the amount of $231,146 for this work.
STRATEGIC PLAN CONNECTION:
NA
BUDGETARY IMPACT:
Budgeted Yes, Partial
If not budgeted, is amendment/transfer attached? Yes
BAF# 23-080-T
Amount Requested ($231,146)
Account Number 424-4055-536.63-00, WS16MM
Account Name Infrastructure
Amount Requested $231,146
Account Number 424-4020-536.63-00, WS23DF
Account Name Infrastructure
If a P.O. Change Order is involved please complete the following:
Change Order Amount $231,146
Original Purchase Order 80847
Original P.O. Amount $424,120
For this Agenda Item note Prior Change Order Information:
Total number of change orders to date 0
Total amount in change orders to date $0
PREVIOUS ACTION:
March 14, 2023 - Award Bid No. B-23-14-COC, Groundwater Filter #3 IMS Cap and Media Replacement, Project No. WS23DF to Elenis Contracting LLC of Poland, Ohio, in the Amount of $424,120; Approve a Resolution Authorizing the City Manager to Approve Change Orders in an amount not to exceed $42,413 (10% of the contract amount), for a total cost of $466,533; Approve a Resolution Amending the FY2023 Budget, BAF# 23-046-T; Authorize the City Manager to execute the Contract
RECOMMENDED MOTION:
Recommendation
Approve a Budget Resolution, Amending the FY2023 Budget, BAF# 23-080-T in the amount of $231,146; Approve Change Order #1 for Elenis Contracting LLC/PO 80847 in the amount of $231,146; Approve Project Resolution Authorizing the City Manager to Issue Change Orders with a Total Project Contingency not to exceed $273,559 for the Dyal Ground Water Filter #3 Project (WS23DF)