Legislation Details

File #: 23-649    Version: 1 Name:
Type: Agenda Status: Agenda Ready
File created: 10/10/2023 In control: City Council
On agenda: 1/23/2024 Final action:
Title: To Approve the Guaranteed Maximum Price (GMP) Proposal #2 from Wharton-Smith, Inc. (WSI) for the Construction Phase Services for the Internal Recycle Pump, Influent Pump Station, and Transfer Pump Station Replacement and Rehabilitation Project (WS22IR) at the Jerry Sellers Water Reclamation Facility; To Authorize the City Manager to Execute Amendment #1 to Task Order 2024-04 and to Execute GMP Amendment #5 to the Master Service Agreement with WSI for Construction Manager at Risk (CMAR) Services; To Authorize the City Manager to Execute Change Orders Resulting from use of Continency; To Approve as a Multi-Year Contract from FY2024 through FY2025; To Approve a Contingency Resolution; To Approve a BAF # 24-043-A and related Budget Resolution #2024-xxx Amending the FY2024 Budget
Attachments: 1. TO 2024-04 - Amendment #5 - GMP#2 Proposal, 2. TO-WHARTON 2024-04.1 $10,133,063.00 - UT-ENGIN.pdf, 3. Wharton Master Services Agreement.pdf, 4. Wharton Bid Fees, 5. WSI Amendment 3.pdf, 6. BAF 24-043-A-PW-IRP, IPS, and TPS Replacement (1-23-24) Agenda 23-649.pdf, 7. Budget Resolution, 8. Contingency Resolution.pdf, 9. COI Wharton Exp 4-1-24.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

Memo Date:                                          January 2, 2024

Agenda Date:                     January 23, 2024

Prepared By:                                          John Perrin, P.E., Senior Engineer

Through:                                          John A. Walsh, P.E., Utilities Director

Requested Action:                     

title

To Approve the Guaranteed Maximum Price (GMP) Proposal #2 from Wharton-Smith, Inc. (WSI) for the Construction Phase Services for the Internal Recycle Pump, Influent Pump Station, and Transfer Pump Station Replacement and Rehabilitation Project (WS22IR) at the Jerry Sellers Water Reclamation Facility; To Authorize the City Manager to Execute Amendment #1 to Task Order 2024-04 and to Execute GMP Amendment #5 to the Master Service Agreement with WSI for Construction Manager at Risk (CMAR) Services; To Authorize the City Manager to Execute Change Orders Resulting from use of Continency; To Approve as a Multi-Year Contract from FY2024 through FY2025; To Approve a Contingency Resolution; To Approve a BAF # 24-043-A and related Budget Resolution #2024-xxx Amending the FY2024 Budget.End

 

body

BACKGROUND:

 

The Advanced Waste Treatment (AWT) requirements per Florida Statute 403.806 mandate stricter limitations on wastewater effluent by July 1, 2025. The result of the statute effectively requires upgrades to the Internal Recycle Pump (IRP) system at the Jerry Sellers Water Reclamation Facility (Sellers WRF) to be in place and fully operational several months prior to the AWT deadline, allowing time for testing and tuning of the system during wet and dry seasons prior to the AWT deadline, in order to meet compliance requirements. The work generally consists of the replacement of pumps, motors, piping, pad mounts, and related appurtenances.

 

In addition to the AWT requirements, the City has been ordered to perform rehabilitation and replacement of components within the Influent Pump Station (IPS), Transfer Pump Station (TPS), and headworks areas of the Sellers WRF pursuant to the requirements of a Consent Order with the Florida Department of Environmental Protection (FDEP). The work generally consists of the replacement of pumps, piping, gates, and related appurtenances, as well as the refurbishment of the concrete basins of the IPS and headworks areas.

 

Due to time and space constraints, the IRP Replacement Project is being consolidated with, and performed in conjunction with, the IPS and TPS Rehabilitation Project.

 

The City of Cocoa has chosen to utilize the Construction Manager at Risk (CMAR) project delivery method for the IRP, IPS, and TPS Replacement and Rehabilitation Projects.  As part of this delivery method, Wharton-Smith, Inc. (WSI) was previously selected and provided preconstruction services during the design of the project. These services supported the City’s Design Engineer during the design to help minimize potential change orders during the construction phase of the project.  The preconstruction services phase of the project is complete and WSI has presented to the City the Guaranteed Maximum Price (GMP) Proposal #2 for the remaining construction services phase of the project, generally consisting of the installation of the long lead items procured under GMP Proposal #1, which was approved by City Council on September 26, 2023.

 

The GMP Proposal #2 includes a statement of the cost of the construction work generally organized by trade categories and includes allowances and fees for the CMAR previously approved by City Council on April 25, 2023. The total cost of this proposal is $10,133,063, of which 6% is a CMAR contingency and 6% is an Owner Contingency totaling $1,215,968. The contingencies will be encumbered into the total cost of the proposal as permissible per the terms of the CMAR continuing services agreement under RFQ-19-04-COC.  The total cost for Amendment #1 to Task Order 2024-04 is $10,133,063, bringing the total cost of the task order to $11,581,208.

$This project is partially funded in FY24. A Budget Adjustment Form (BAF) is necessary to allocate additional funding to Project Number WS22IR Account Number 424-4055-536.63-00 (Infrastructure) from the following project:

•                     Project Number WS23SC Account Number 424-4055-536.63-00 (Infrastructure)

 

Staff reviewed and recommends approval of this agenda item including the GMP Proposal #2 with WSI for the construction phase services for the IRP, IPS, and TPS Replacement and Rehabilitation Project at Sellers WRF.

 

 

STRATEGIC PLAN CONNECTION: 

 

N/A

 

 

BUDGETARY IMPACT:

 

Budgeted                                                                                                                                                   Partial

If not budgeted, is amendment/transfer attached?                     Yes

 

Budgeted Amount                     $6,450,620.36

 

Amount Requested                                          $3,682,443

Account Number                                          424-4055-536.63-00 WS22IR

Account Name                                          Infrastructure

 

Source of Funds:                                 424-0000-389.99-50                     $3,382,443

                                                                                    424-4055-536.63-00                          300,000                     WS23SC

 

If a P.O. Change Order is involved please complete the following:

 

Change Order Amount                      $_10,133,063

 

Original Purchase Order                       81414

Original P.O. Amount                      _$1,448,145

For this Agenda Item note Prior Change Order Information:

Total number of change orders to date _1 (including this requested change order)

Total amount in change orders to date _$10,133,063 (including this requested change order)

Total amount of Purchase Order #81414 including all change orders to date $11,581,208

 

 

PREVIOUS ACTION:

 

On October 24, 2018, City Council approved the Final Ranking of the Firms for RFQ-19-04-COC, Construction Manager at Risk (CMAR) Services for Water and Wastewater Plant Project and authorized the City Manager and City Attorney to Negotiate and Execute a Multi-Year Contract with the Three Top-Ranked Firms; Wharton-Smith, Inc., Garney Companies, Inc., and Petticoat-Schmitt Civil Contractors, Inc.

 

On August 23, 2022, City Council approved a Resolution waiving the competitive bidding process for the construction of the IPS Rehabilitation Project, and approved Amendments adding the IPS Rehabilitation Project to the scope of possible wastewater projects to the Master Services Agreements for CMAR services.

 

On April 25, 2023, City Council approved the Scope of Services as a multi-year contract with WSI for CMAR Services for the IRP, IPS, and TPS Replacement and Rehabilitation Project at the Sellers WRF.

 

On September 26, 2023, City Council approved the GMP Proposal #1 and Amendment #4 to the Master Service Agreement under RFQ-19-04-COC with WSI for limited construction phase services for the IRP, IPS, and TPS Replacement and Rehabilitation Project at the Sellers WRF.

 

RECOMMENDED MOTION:

Recommendation

To Approve the Guaranteed Maximum Price (GMP) Proposal #2 from Wharton-Smith, Inc. (WSI) for the Construction Phase Services for the Internal Recycle Pump, Influent Pump Station, and Transfer Pump Station Replacement and Rehabilitation Project (WS22IR) at the Jerry Sellers Water Reclamation Facility; To Authorize the City Manager to Execute Amendment #1 to Task Order 2024-04 and to Execute GMP Amendment #5 to the Master Service Agreement with WSI for Construction Manager at Risk (CMAR) Services; To Authorize the City Manager to Execute Change Orders Resulting from use of Continency; To Approve as a Multi-Year Contract from FY2024 through FY2025; To Approve a Contingency Resolution; To Approve a BAF # 24-043-A and related Budget Resolution #2024-xxx Amending the FY2024 Budget.