File #: 24-058    Version: 1 Name:
Type: Agenda Status: Agenda Ready
File created: 1/30/2024 In control: City Council
On agenda: 2/27/2024 Final action:
Title: To Approve Task Order 2024-09 with Atlantic Development of Cocoa, Inc. for Construction of the Osage/Angelica Utilities Improvements Project; To Approve as a Multi-Year Contract; To Approve a Resolution Authorizing the City Manager to Approve and Execute Change Orders in an Amount Not To Exceed $371,738.53 (10% of the Contract Amount) for a Total Project Cost of $4,089,123.83; To Approve a Resolution Amending the FY2024 Budget, BAF#24-058-IFT
Attachments: 1. Settlement Agreement.pdf, 2. Agreement for Utilities General Construction Contractor Atlantic.pdf, 3. 1st Amendment Atlantic Fully Ex.pdf, 4. Angelica-Osage Quote Package.pdf, 5. Appendix B - Osage Angelica Bid Plans.pdf, 6. Osage-Angelica Quote Tabulation Sheet.pdf, 7. TO-ATLANTIC DEV 2024-09 $3,717,385.30 - UT_ENGIN.pdf, 8. Osage_Angelica Utilities Improvements Bid from Atlantic Development of Cocoa.pdf, 9. Contingency Resolution - Osage-Angelica.pdf, 10. Budget Resolution Osage-Angelica.pdf, 11. Tracking Sheet BAF 24-058-IFT.pdf, 12. BAF 24-058-IFT-UT-Osage-Angelica Utility Improvement (2-27-24) Agenda 24-059.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

Memo Date:                                          January 30, 2024

Agenda Date:                     February 27, 2024

Prepared By:                                          Katherine D. Ennis, P.E., Deputy Utilities Director

Through:                                          John A. Walsh, P.E., Utilities Director

Requested Action:                     

title

To Approve Task Order 2024-09 with Atlantic Development of Cocoa, Inc. for Construction of the Osage/Angelica Utilities Improvements Project; To Approve as a Multi-Year Contract; To Approve a Resolution Authorizing the City Manager to Approve and Execute Change Orders in an Amount Not To Exceed $371,738.53 (10% of the Contract Amount) for a Total Project Cost of $4,089,123.83; To Approve a Resolution Amending the FY2024 Budget, BAF#24-058-IFT.....End

 

body

BACKGROUND:

 

The City of Cocoa and the Virgin Trains USA Florida, LLC executed a Settlement Implementation Agreement pursuant to two previous Development Agreements the property located at I-95 and State Road 528.  The City of Cocoa has agreed to design, permit and construct water, sewer and reclaim services to this property subject to certain terms for development. 

  

In February 2021, Council approved Task Order 2021-21 for the design of the Utility Extensions (water, sewer, reclaim) with Bussen Mayer Engineering Group (currently DRMP, Inc.). The design was completed as two separate design segments, Friday Road Extension and the Osage/Angelica Extension. The project was split into two separate segments as they are not contiguous segments and also allows for flexibility in the timing/schedule of construction based on the needs of the overall project. The designs were completed in December of 2023.

 

DRMP will also be perform the engineering services during construction (SDC), pending City Council approval.

 

On February 7, 2024, the City of Cocoa solicited quotes for the Osage/Angelica Utilities Improvements Project from three (3) continuing service contractors pre-qualified by the City of Cocoa Utilities Department under RFQ 20-18-COC City of Cocoa General Contractor - Utility Systems. The following responses were received:

 

•                     Atlantic Development of Cocoa, Inc. - $3,717,385.30;

•                     Danus Utilities, Inc. - $4,110,400.70;

•                     Hinterland Group, Inc. - Did Not Submit a Response.

 

Staff is requesting City Council approval of Task Order 2024-09 with Atlantic Development of Cocoa, Inc. for construction of the Osage/Angelica Utilities Improvements Project as a multi-year contract.

 

Staff is also requesting that City Council approve an additional $371,738.53 as contingency for the project.  The additional amount is 10% of the contract amount and will be used for change orders with approval by the City Manager.  Although City staff does not anticipate change orders, with a project of this size there is always a possibility of unknown obstacles in the field that would require changes to the project.  If a change order is needed, the additional amount will allow the project to continue forward while minimizing delays.

 

The additional $371,738.53 for Construction Contingency Budget will not be added to the initial purchase order.  Each change order will be reviewed by staff before it is sent to the City Manager for approval, and subsequently added to the purchase order.

 

Staff recommends approval of Task Order 2024-09 with Atlantic Development of Cocoa, Inc. for construction of the Osage/Angelica Utilities Improvements Project.

 

This project is partially funded in FY24. A Budget Adjustment Form (BAF) is necessary to allocate additional funding from Account Number XX to Project Number WS21CG Account Number 421-4055-536.63-00 (Infrastructure).

 

Contractor Bid                                                                                                                                                                        $3,717,385.30

Construction Contingency                                                                                                                                                        $371,738.53 (10%)

 

Total Project Cost:                                                                                                                                                                                $4,089,123.83

 

 

 

STRATEGIC PLAN CONNECTION: 

 

NA

 

 

BUDGETARY IMPACT:

 

Budgeted                                                                                                                                                   Yes, Partial

If not budgeted, is amendment/transfer attached?                     Yes

 

BAF#24-058-ITF-See Tracking Sheet

Amount Requested                                          $4,089,125

Account Number                                          424-4055-536.63-00 WS24LC

Account Name                                          Infrastructure

 

Source of Funds:                     Impact Fees                     and Original Budget WS21CG                                                                                    

 

 

TOTAL COST FOR MULTI-YEAR CONTRACT:                          $4,089,125

 

 

PREVIOUS ACTION:

 

February 9, 2021 - Approved Task Order 2021-21 with Bussen Mayer Engineering Group, Inc. for Professional Engineering and Consulting Services for the Lakes at Cocoa Grove - Utility Extensions, Project No. WS21CG; Approved a Resolution Amending the FY2021 Budget, BAF #21-045-T

 

RECOMMENDED MOTION:

Recommendation

To Approve Task Order 2024-09 with Atlantic Development of Cocoa, Inc. for Construction of the Osage/Angelica Utilities Improvements Project; To Approve as a Multi-Year Contract; To Approve a Resolution Authorizing the City Manager to Approve and Execute Change Orders in an Amount Not to Exceed $371,738.53 (10% of the Contract Amount) for a Total Project Cost of $4,089,123.83; To Approve a Resolution Amending the FY2024 Budget, BAF#24-058-IFT.....