Skip to main content

Closed captioned livestreams and replays of all City of Cocoa City Council meetings can be found on the City's YouTube Channel. Simply click on the "CC" in the bottom right corner of the video.

File #: 23-723    Version: 1 Name:
Type: Agenda Status: Agenda Ready
File created: 11/9/2023 In control: City Council
On agenda: 11/14/2023 Final action:
Title: Approval of a Final Subdivision Plat known as Adamson Creek Phase Two consistent with Chapter 18 Subdivisions and Appendix A Zoning of the City Code, with conditions.
Attachments: 1. Adamson Cree Phase 2 - CITY-FINAL PLAT_11-01-2023.pdf, 2. Exhibit A - AC Ph2 Location Map.pdf, 3. Exhibit B - Engineer Opinion of Cost_Perf Bond_Subdivion_2023-11-08.pdf, 4. Exhibit C - Engineer Opinion of Cost_Perf Bond_Amenities_2023-11-08.pdf, 5. Exhibit Conservation Area Map.pdf, 6. Exhibit D - PH2-Original Performance Bond Cost Cert.pdf, 7. Exhibit E Legal Ad.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

Memo Date: November 8, 2023
Agenda Date: November 14, 2023
Prepared By: Lucilene Ribeiro - Planner
Through: Stockton Whitten - City Manager
Requested Action:
title
Approval of a Final Subdivision Plat known as Adamson Creek Phase Two consistent with Chapter 18 Subdivisions and Appendix A Zoning of the City Code, with conditions.
End

body
BACKGROUND:

The Adamson Creek subdivision project was first approved as a Planned Unit Development (PUD) in 2005/2006 consisting of 431 single-family homes on 178 acres with 44 acres of open space and amenities. Phase 1 was approved and recorded in 2006. Due to a slowdown in the housing market triggered by the recession, Phase 1 was later broken down into 3 phases (1A, 1B, and 1C) of which Phase 1A was recorded in 2007 with 154 single-family homes.

The subject property, Adamson Creek Phase Two, is located on the east side of Adamson Road and to the south of the previously developed Adamson Creek neighborhood (Exhibit A - Location Map) and is considered a standalone PUD.

This phase will include 30 single-family homes on a single street and will provide common recreational space amenities, including a walking path surrounding a stocked stormwater pond, a fishing platform, and other open space areas.

On August 22, 2023, the City approved a Preliminary Subdivision for Phase Two, a one (1) parcel rezoning (Ordinance 10-2023), a Development Agreement, and a Large-Scale Site Plan.

Project Information:

Phase Two of the project contains 79.13 acres overall, with 14.39 acres of developable land (streets, houses, stormwater ponds, and amenities) and 64.74 acres of wetlands and uplands that will be placed into a conservation easement, as shown in Tract C of the final subdivision plat. This phase will include 30 single-family homes on a single private street connecting to Adamson Road through Talbot Blvd.

A dock/viewing platform looking at a stocked fish pond is accessed through a trail that run...