File #: 24-295    Version: 1 Name:
Type: Contract Status: Agenda Ready
File created: 5/13/2024 In control: City Council
On agenda: 7/9/2024 Final action:
Title: To Approve a Purchase Order and Agreement with Tech Systems, Inc. for a new roof system on Wewahootee Pump Station piggybacking a Brevard County Continuing Roofing Contracting Services contract, RFQ 6-22-13, Effective May 12, 2023 through May 12, 2025; To Approve a Resolution Authorizing the City Manager to Approve and Execute Change Orders in an Amount Not to Exceed $10,683.40 (10% of the Contract Amount) for a Total Combined Project Cost of $117,517.37
Attachments: 1. Wewahootee Roof Replacement 2024 - updated.pdf, 2. Resolution 2024-056 - Project Contingency (Tech Systems).pdf, 3. First Renewal Continuing Roofing Contracts.pdf, 4. RFQ-6-22-13 Roofing Contract TechSystems-EXE-20230512.pdf, 5. FULLY EXECUTED 1st Amendment Renewal Contract No RFQ-6-22-13.pdf, 6. Cocoa_TCR_WewaPump_Roof_Rehab_Bid_Docs_rev2.pdf, 7. SIGNED E-Verify Contractor Affidavit.pdf, 8. Tech Systems, Inc Auto COI Exp.07.01.2024.pdf, 9. Tech Systems, Inc. Auto COI 2 Exp.09.01.2024.pdf, 10. Tech Systems, Inc. Auto COI Exp.09.01.2024.pdf, 11. Tech Systems, Inc. COI Exp.07.01.2024.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

Memo Date: June 3, 2024
Agenda Date: July 9, 2024
Prepared By: James Mitchell, Water Treatment Manager
Through: John A. Walsh, P.E., Utilities Director
Requested Action:
title
To Approve a Purchase Order and Agreement with Tech Systems, Inc. for a new roof system on Wewahootee Pump Station piggybacking a Brevard County Continuing Roofing Contracting Services contract, RFQ 6-22-13, Effective May 12, 2023 through May 12, 2025; To Approve a Resolution Authorizing the City Manager to Approve and Execute Change Orders in an Amount Not to Exceed $10,683.40 (10% of the Contract Amount) for a Total Combined Project Cost of $117,517.37End

body
BACKGROUND:

The Wewahootee Pump Station High Service Pump/MCC building contains four raw water pumps, an electrical room, and an employee kitchen and bathroom.

An inspection of this original roof revealed that it has reached the end of its useful life and requires replacement, thus protecting the sensitive water treatment controls located inside.

Staff requests City Council approval of the roof replacement cost in the amount of $106,833.97. City staff is also requesting that City Council approve an additional $10,683.40 (10%) as a contingency for the project. The total amount of the project including the 10% contingency is $117,517.37. The additional amount is requested to cover any additional time and materials that may be required in excess of the original proposal. Although City staff does not anticipate any change orders, there is a possibility that unforeseen events would require changes to the project scope. If a change order is required, the additional amount will allow the project to continue moving forward.

The additional $10,683.40 will not be added to the initial purchase order and each change order will be reviewed by staff before it is sent to the City Manager for approval.


STRATEGIC PLAN CONNECTION:

N/A


BUDGETARY IMPACT:

Budgeted Yes
If not budgeted, is amendmen...