File #: 23-649    Version: 1 Name:
Type: Agenda Status: Agenda Ready
File created: 10/10/2023 In control: City Council
On agenda: 1/23/2024 Final action:
Title: To Approve the Guaranteed Maximum Price (GMP) Proposal #2 from Wharton-Smith, Inc. (WSI) for the Construction Phase Services for the Internal Recycle Pump, Influent Pump Station, and Transfer Pump Station Replacement and Rehabilitation Project (WS22IR) at the Jerry Sellers Water Reclamation Facility; To Authorize the City Manager to Execute Amendment #1 to Task Order 2024-04 and to Execute GMP Amendment #5 to the Master Service Agreement with WSI for Construction Manager at Risk (CMAR) Services; To Authorize the City Manager to Execute Change Orders Resulting from use of Continency; To Approve as a Multi-Year Contract from FY2024 through FY2025; To Approve a Contingency Resolution; To Approve a BAF # 24-043-A and related Budget Resolution #2024-xxx Amending the FY2024 Budget
Attachments: 1. TO 2024-04 - Amendment #5 - GMP#2 Proposal, 2. TO-WHARTON 2024-04.1 $10,133,063.00 - UT-ENGIN.pdf, 3. Wharton Master Services Agreement.pdf, 4. Wharton Bid Fees, 5. WSI Amendment 3.pdf, 6. BAF 24-043-A-PW-IRP, IPS, and TPS Replacement (1-23-24) Agenda 23-649.pdf, 7. Budget Resolution, 8. Contingency Resolution.pdf, 9. COI Wharton Exp 4-1-24.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

Memo Date: January 2, 2024
Agenda Date: January 23, 2024
Prepared By: John Perrin, P.E., Senior Engineer
Through: John A. Walsh, P.E., Utilities Director
Requested Action:
title
To Approve the Guaranteed Maximum Price (GMP) Proposal #2 from Wharton-Smith, Inc. (WSI) for the Construction Phase Services for the Internal Recycle Pump, Influent Pump Station, and Transfer Pump Station Replacement and Rehabilitation Project (WS22IR) at the Jerry Sellers Water Reclamation Facility; To Authorize the City Manager to Execute Amendment #1 to Task Order 2024-04 and to Execute GMP Amendment #5 to the Master Service Agreement with WSI for Construction Manager at Risk (CMAR) Services; To Authorize the City Manager to Execute Change Orders Resulting from use of Continency; To Approve as a Multi-Year Contract from FY2024 through FY2025; To Approve a Contingency Resolution; To Approve a BAF # 24-043-A and related Budget Resolution #2024-xxx Amending the FY2024 Budget...End

body
BACKGROUND:

The Advanced Waste Treatment (AWT) requirements per Florida Statute 403.806 mandate stricter limitations on wastewater effluent by July 1, 2025. The result of the statute effectively requires upgrades to the Internal Recycle Pump (IRP) system at the Jerry Sellers Water Reclamation Facility (Sellers WRF) to be in place and fully operational several months prior to the AWT deadline, allowing time for testing and tuning of the system during wet and dry seasons prior to the AWT deadline, in order to meet compliance requirements. The work generally consists of the replacement of pumps, motors, piping, pad mounts, and related appurtenances.

In addition to the AWT requirements, the City has been ordered to perform rehabilitation and replacement of components within the Influent Pump Station (IPS), Transfer Pump Station (TPS), and headworks areas of the Sellers WRF pursuant to the requirements of a Consent Order with the Florida Department of Environmental Protection ...

Click here for full text