Title: To Approve a Multi-Year Task Order 2024-07 with Mead & Hunt, Inc. for Engineering Services for the Design, Permitting and Services to Replace the Day Dock Facility and RipRap Revetment at Lee Wenner Park.
Attachments: 1. TO-MEAD & HUNT 2024-07 $165,980.00 - PW-CP.pdf, 2. CO Lee Wenner park Day Docks Permitting Scope Combined.pdf, 3. Q-23-01-COC-C1 Approval of Subconsultant_Taylor.pdf, 4. Q-23-01-COC-C1 Approval of Subconsultant_Arc.pdf, 5. Mead & Hunt COI exp. 7.1.24.pdf, 6. TRACK SHEET.pdf, 7. CSA-General Civil Engineering-Mead & Hunt.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

Memo Date: June 5, 2024
Agenda Date: July 23, 2024
Prepared By: Shawny Chung, Contract Technician
Through: Abigail Morgan, P.E., Public Works Director
Requested Action:
title
To Approve a Multi-Year Task Order 2024-07 with Mead & Hunt, Inc. for Engineering Services for the Design, Permitting and Services to Replace the Day Dock Facility and RipRap Revetment at Lee Wenner Park.
End

body
BACKGROUND:

Wave conditions caused by Hurricane Nicole destroyed the day dock facility at Lee Wenner Park. The CITY wishes to develop preliminary (permit-level) engineering design and seek environmental permits to replace the docks and construct a riprap revetment along the existing bulkhead shoreline. The riprap revetment would serve to reduce reflected wave energy and minimize structural damage during future coastal storms.

Scope of work includes the following:

Phase 1 - Project Management and Meetings
Phase 2 - Data Collection and Site Reconnaissance
Phase 3 - Coastal Analysis and Design Wave Assessment
Phase 4 - Preliminary (Permit-Level) Engineering Design
Phase 5 - Environmental Permitting

Staff recommends approval of a Multi-Year Task Order 2024-07 with Mead & Hunt, Inc. for the Design, Permitting and Services to Replace the Day Dock Facility and RipRap Revetment at Lee Wenner Park project GR2404 for $165,980.00.


STRATEGIC PLAN CONNECTION:

Improving the waterfront infrastructure will increase economic development within the City.

BUDGETARY IMPACT:

Budgeted Yes
If not budgeted, is amendment/transfer attached? N/A

Amount Requested $165,980.00
Account Number 304-3580-572.63-00 GR2404
Account Name Parks and Recreation/Infrastructure
Source of Funds FIND Grant/Cocoa CRA


PREVIOUS ACTION:

Council approved the grant application 3/14/23. The CRA board approved the 50% Match Funding on 12/4/23 to the Capital Project Fund 304. Agenda 23-709 was approved on 12/12/23 to Authorize the City Manager to Execute...