Closed captioned livestreams and replays of all City of Cocoa City Council meetings can be found on the City's YouTube Channel. Simply click on the "CC" in the bottom right corner of the video.

File #: 21-468    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 6/24/2021 In control: City Council
On agenda: 7/27/2021 Final action:
Title: To Approve an Increase to the Contingency for the Wewahootee Sulfuraetor Rehabilitation and Aluminum Dome Repair Project (WS21WS) in the Amount of $34,155 for a Total Project Contingency of $53,950; To Authorize the City Manager to Approve Change Orders to P.O. 78016 with Vortex Services, LLC in an Amount not to Exceed $53,950; To Approve a Resolution Amending the FY2021 Budget; BAF # 21-090-A
Attachments: 1. Proposal-203436-CO-1-FL-Cocoa-Sulfuraetor Caps Rehab.pdf, 2. Vortex_Quote_agenda.pdf, 3. Budget Resolution 7.27.21.pdf, 4. BAF 21-090-A-UT-Protection of Sulfuraetor Tanks (7-27-21) Agenda 21-468.pdf, 5. Amendment 1 contract extension TP07-18-Vortex Services LLC.pdf, 6. PO# 78016.pdf, 7. Vortex Services COI EXP 12.11.21.pdf, 8. Resolution 2021-065 Contingency Vortex.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

Memo Date: June 24, 2021
Agenda Date: July 27, 2021
Prepared By: Sean B. McFarland, Water Treatment Manager
Through: John A. Walsh, P.E., Utilities Director
Requested Action:
title
To Approve an Increase to the Contingency for the Wewahootee Sulfuraetor Rehabilitation and Aluminum Dome Repair Project (WS21WS) in the Amount of $34,155 for a Total Project Contingency of $53,950; To Authorize the City Manager to Approve Change Orders to P.O. 78016 with Vortex Services, LLC in an Amount not to Exceed $53,950; To Approve a Resolution Amending the FY2021 Budget; BAF # 21-090-A
End

body
BACKGROUND:

The Dyal WTP staff is requesting that City Council approve an increase to the previously approved contingency amount and associated budget transfer for the Sulfuraetor Rehabilitation and Aluminum Dome Repair project (WS21WS).
On April 27, 2021, City Council approved an initial contingency amount of $19,795 (10%) related to this project. A recent preconstruction visit conducted on May 25, 2021 by Vortex Services, LLC and Dyal WTP staff revealed the need for additional epoxy coating/lining that is required to ensure additional protection of the existing concrete structures. Subsequent to the preconstruction visit, a revised estimated project total was submitted by Vortex Services, LLC and is attached as part of this agenda item.
The total contingency requested is $53,950 which is an increase of $34,155 over the previously approved contingency amount of $19,795. The requested funds that were not originally budgeted will be transferred from Account No. 421-4020-536.43-00 (Electric) are available order to meet this request.
Staff is requesting the approval of the contingency increase amount for a total project contingency of $53,950.

STRATEGIC PLAN CONNECTION:

N/A


BUDGETARY IMPACT:

Budgeted No
If not budgeted, is amendment/transfer attached? Yes, BAF # 21-090-A

Amount Requested $34,155
Account Number 424-4020-536.63-0...

Click here for full text