Closed captioned livestreams and replays of all City of Cocoa City Council meetings can be found on the City's YouTube Channel. Simply click on the "CC" in the bottom right corner of the video.

File #: 22-568    Version: 1 Name:
Type: Contract Status: Multi-Year Contract
File created: 9/16/2022 In control: City Council
On agenda: 9/27/2022 Final action:
Title: Approve a purchase order with V.A. Paving Inc. in the amount of $295,128.05, plus a contingency of $4,871.95 for a total of $300,000, using the Second Amendment to the Piggyback Agreement with V.A. Paving, No. B-6-20-57, from August 22, 2022, through August 21, 2023, to resurface various stretches of roads throughout the City, pending the approval of FY 23 budget.
Attachments: 1. Brevard County Bid No. B-6-20-57.pdf, 2. BrevardCounty Paving Renewal 8-22-22 to 8-21-23.pdf, 3. 2nd Amendment to VA Paving Inc., Asphaltic Concrete B-6-20-57 (2).pdf, 4. Fully Executed Piggyback Contract Agreement.pdf, 5. Annual Paving Agenda Item 21-675.pdf, 6. VA Paving - City of Cocoa 2023 Annual Resurfacing 9.9.22.pdf, 7. VA Paving COI exp 12-31-22.pdf, 8. Resolution - Annual Street Paving Project Contingency.pdf, 9. B-6-20-57 - Price Adjustment 6 - V.A. Paving.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

Memo Date:                                          September 16, 2022

Agenda Date:                     September 27, 2022

Prepared By:                                          Abigail Morgan, P.E., Public Works Assistant City Engineer

Through:                                          Bryant Smith III, P.E., CFM, Public Works Director/ 

Requested Action:                     

title

Approve a purchase order with V.A. Paving Inc. in the amount of $295,128.05, plus a contingency of $4,871.95 for a total of $300,000, using the Second Amendment to the Piggyback Agreement with V.A. Paving, No. B-6-20-57, from August 22, 2022, through August 21, 2023, to resurface various stretches of roads throughout the City, pending the approval of FY 23 budget. End

 

body

BACKGROUND:

 

The Public Works Department has an annual repaving program to address roads that are in failing or poor condition. In 2015, the city completed an entire analysis of the road and sidewalk network. The analysis included the evaluation of the pavement condition, roadway structural condition, and sidewalk trip hazards. The study is updated annually through the use of Staff evaluation, work orders, and GIS and serves as a guiding program to address the City’s needs. While the roadway conditions are scored through an industry-standard degradation schedule, staff also performs on-site analysis to ensure resources are allocated in the best manner.

 

This fiscal year the following streets are scheduled to be milled and paved. 

 

Street Name

From

To

Pinyon Dr

Cox Rd

SR 524

Longleaf Rd

Pinyon Dr

Pinyon Dr

Ponderosa St

Pinyon Dr

Longleaf Rd

S Varr Ave

SR 520

Peachtree St

Ridgeway Ave

SR 520

Peachtree St

St Johns St

US 1

Ridgeway Ave

Washington Ave

SR 520

S Wilson Ave

St Johns St

Washington Ave

Blake Ave

Ivy Dr

College Ave

Terminus

Cooper Dr

East Stetson Circle

East Stetson Circle

Cambridge

Cambridge School

Westview

 

The following streets are tentatively scheduled for the following fiscal year.

 

Street

From

To

Elizabeth Ave

Kensington Dr

Hillsdale Dr

Donna Ave

Kensington Dr

Hillsdale Dr

Donna Ave

Hillsdale Dr

END

Donna Ave

Kensington Dr

END

Hillsdale Dr

Elizabeth Ave

Donna Ave

Hillsdale Dr

Carson Dr

Elizabeth Ave

Hillsdale Dr

Westview

Carson Dr

Hillsdale Dr

Kensington Dr

Westview

Hillsdale Dr

Donna Ave

END

Kensington Dr

Fiske Blvd

Hillsdale Dr

Kensington Dr

Elizabeth Ave

Donna Ave

Kensington Dr

Hillsdale Dr

Elizabeth Ave

Cambridge

Cambridge School

Harvard

Harvard

Cambridge School

Westview

Townsend Rd

SR520

City Limits

 

Please note that streets may be added or removed from the FY 23 paving lists based on unforeseen circumstances, additional investigation, or project over/underruns.

 

 

STRATEGIC PLAN CONNECTION: 

 

Road repair and maintenance are essential in order to (1) preserve the road in its originally

constructed condition, (2) protect adjacent resources and user safety, and (3) provide efficient, convenient travel along the route.

 

 

BUDGETARY IMPACT:

 

Budgeted                                                                                                                                                   Yes

If not budgeted, is amendment/transfer attached?                     Choose an item.

 

Pending Adoption of FY 23 Budget

 

Milling and Paving of Streets

Amount Requested                                          $295,128.05

Account Number                                          _001-3510-541.63-00 PW08SP

Account Name                                          _Infrastructure

 

Allow City Manager to Approve Change Orders

Amount Requested                                          $4,871.95

Account Number                                          _001-3510-541.63-00 PW08SP

Account Name                                          _Infrastructure

 

Not to exceed a total of $300,000.

 

 

PREVIOUS ACTION:

 

This project is part of the City’s annual repaving plan.

 

RECOMMENDED MOTION:

Recommendation

Approve a purchase order with V.A. Paving Inc. in the amount of $295,128.05, plus a contingency of $4,871.95 for a total of $300,000, using the Second Amendment to the Piggyback Agreement with V.A. Paving, No. B-6-20-57, from August 22, 2022, through August 21, 2023, to resurface various stretches of roads throughout the City, pending the approval of FY 23 budget.