CITY COUNCIL AGENDA ITEM
Memo Date: September 16, 2022
Agenda Date: September 27, 2022
Prepared By: Abigail Morgan, P.E., Public Works Assistant City Engineer
Through: Bryant Smith III, P.E., CFM, Public Works Director/
Requested Action:
title
Approve a purchase order with V.A. Paving Inc. in the amount of $295,128.05, plus a contingency of $4,871.95 for a total of $300,000, using the Second Amendment to the Piggyback Agreement with V.A. Paving, No. B-6-20-57, from August 22, 2022, through August 21, 2023, to resurface various stretches of roads throughout the City, pending the approval of FY 23 budget. End
body
BACKGROUND:
The Public Works Department has an annual repaving program to address roads that are in failing or poor condition. In 2015, the city completed an entire analysis of the road and sidewalk network. The analysis included the evaluation of the pavement condition, roadway structural condition, and sidewalk trip hazards. The study is updated annually through the use of Staff evaluation, work orders, and GIS and serves as a guiding program to address the City’s needs. While the roadway conditions are scored through an industry-standard degradation schedule, staff also performs on-site analysis to ensure resources are allocated in the best manner.
This fiscal year the following streets are scheduled to be milled and paved.
Street Name |
From |
To |
Pinyon Dr |
Cox Rd |
SR 524 |
Longleaf Rd |
Pinyon Dr |
Pinyon Dr |
Ponderosa St |
Pinyon Dr |
Longleaf Rd |
S Varr Ave |
SR 520 |
Peachtree St |
Ridgeway Ave |
SR 520 |
Peachtree St |
St Johns St |
US 1 |
Ridgeway Ave |
Washington Ave |
SR 520 |
S Wilson Ave |
St Johns St |
Washington Ave |
Blake Ave |
Ivy Dr |
College Ave |
Terminus |
Cooper Dr |
East Stetson Circle |
East Stetson Circle |
Cambridge |
Cambridge School |
Westview |
The following streets are tentatively scheduled for the following fiscal year.
Street |
From |
To |
Elizabeth Ave |
Kensington Dr |
Hillsdale Dr |
Donna Ave |
Kensington Dr |
Hillsdale Dr |
Donna Ave |
Hillsdale Dr |
END |
Donna Ave |
Kensington Dr |
END |
Hillsdale Dr |
Elizabeth Ave |
Donna Ave |
Hillsdale Dr |
Carson Dr |
Elizabeth Ave |
Hillsdale Dr |
Westview |
Carson Dr |
Hillsdale Dr |
Kensington Dr |
Westview |
Hillsdale Dr |
Donna Ave |
END |
Kensington Dr |
Fiske Blvd |
Hillsdale Dr |
Kensington Dr |
Elizabeth Ave |
Donna Ave |
Kensington Dr |
Hillsdale Dr |
Elizabeth Ave |
Cambridge |
Cambridge School |
Harvard |
Harvard |
Cambridge School |
Westview |
Townsend Rd |
SR520 |
City Limits |
Please note that streets may be added or removed from the FY 23 paving lists based on unforeseen circumstances, additional investigation, or project over/underruns.
STRATEGIC PLAN CONNECTION:
Road repair and maintenance are essential in order to (1) preserve the road in its originally
constructed condition, (2) protect adjacent resources and user safety, and (3) provide efficient, convenient travel along the route.
BUDGETARY IMPACT:
Budgeted Yes
If not budgeted, is amendment/transfer attached? Choose an item.
Pending Adoption of FY 23 Budget
Milling and Paving of Streets
Amount Requested $295,128.05
Account Number _001-3510-541.63-00 PW08SP
Account Name _Infrastructure
Allow City Manager to Approve Change Orders
Amount Requested $4,871.95
Account Number _001-3510-541.63-00 PW08SP
Account Name _Infrastructure
Not to exceed a total of $300,000.
PREVIOUS ACTION:
This project is part of the City’s annual repaving plan.
RECOMMENDED MOTION:
Recommendation
Approve a purchase order with V.A. Paving Inc. in the amount of $295,128.05, plus a contingency of $4,871.95 for a total of $300,000, using the Second Amendment to the Piggyback Agreement with V.A. Paving, No. B-6-20-57, from August 22, 2022, through August 21, 2023, to resurface various stretches of roads throughout the City, pending the approval of FY 23 budget.