CITY COUNCIL AGENDA ITEM
Memo Date: May 15, 2023
Agenda Date: June 6, 2023
Prepared By: Katherine D. Ennis, P.E., Deputy Utilities Director
Through: John A. Walsh, P.E., Utilities Director
Requested Action:
title
Approve a Budget Resolution, Amending the FY2023 Budget, BAF# 23-080-T in the amount of $231,146; Approve Change Order #1 for Elenis Contracting LLC/PO 80847 in the amount of $231,146; Approve Project Resolution Authorizing the City Manager to Issue Change Orders with a Total Project Contingency not to exceed $273,559 for the Dyal Ground Water Filter #3 Project (WS23DF)
End
body
BACKGROUND:
On March 14, 2023 Council approved award of the project to Elenis Contracting LLC in the amount of $424,120. Council also authorized the City Manager to Approve and Execute Change Orders in an Amount Not to Exceed $42,412 (10% of the Contract Amount).
The dual media filters at the Dyal Water Treatment Plant are used to remove suspended solids from water. The filters are cleaned periodically with water and air so that the media can be reused. With time, however, the media exhausts its removal capabilities and needs to be exchanged.
This project's original scope was for the replacement of the media, as well as parts of the underdrain system (the IMS caps), which have become clogged with sediment and scaling in filter #3. An inspection of the filter equipment was performed by the contractor and the manufacturer of the equipment (Leopold) once the exhausted media had been removed from the filter. It was determined that there is damage to the underdrains which will require replacement. This additional scope was not known at the time of bid.
The contractor has submitted a quote for the additional scope. The cost for this additional work is $231,146 which is greater than the current available contingency amount.
Staff is requesting approval of the budget resolution, project contingency resolution, and the approval of Change Order #1 in the amount of $231,146...
Click here for full text